sheer tools
Read your own numbers

Lesson 4 of 8 · 7 min

Break-even

Break-even is fixed costs divided by contribution per unit. It is a single number that tells you how much work must happen before you earn anything, and most owners have never calculated it.

A worked example

Fixed costs per month        $12,000
Average project price         $4,000
Variable cost per project     $1,600  (contractor + tools)
Contribution per project      $2,400

Break-even = 12,000 / 2,400 =  5 projects a month

Once you know it is five, everything gets more concrete. A sixth project is not "more revenue," it is the first project of the month that is actually yours. A month with four is not slightly bad, it is a loss.

Three levers, not one

  • Raise price: the fastest lever, because it flows straight into contribution.
  • Cut variable cost: helps every future sale, usually slower to move.
  • Cut fixed cost: lowers the bar immediately, but shrinks capacity.

Notice that selling more is not on the list. Volume is how you use the levers, not a lever itself — and it is the only one that costs you time you may not have.

Try it

Calculate your break-even in units and in revenue. Then recalculate it with a 10% price increase. The gap between those two numbers is the strongest argument for pricing you will ever see.